The Seattle Department of Transportation's weekly transportation construction update highlights the projects and events that may impact travel through the Seattle area. View this week's update.

This week's highlights: 

  • Feb. 5 - 19: Fauntleroy Way SW and SW Wildwood Place intersection closed while crews replace concrete panels and install ADA curb ramps.
  • Feb. 7 - 11: 2018 Northwest Flower and Garden Show at the Washington State Convention Center.
  • Feb. 9: 1st Avenue S. reduced to one lane in each direction between Railroad Way S. and S. Royal Brougham Way for approximately 3 months during the installation of a new electrical duct bank.
  • Feb. 10 - 18: Weekend lane closures on 2nd Avenue between Virginia and Pike streets during crane work.
  • Feb. 11: Water shutoff scheduled in Pioneer Square on Sunday night, 7 p.m. - 5 a.m.
  • Feb. 12 - 16: Howell Street reduced to one lane between 9th and Boren avenues from 7 a.m. to 3 p.m. during sewer line work.

If you have questions, contact construction.coordination@seattle.gov or call 206-684-ROAD.