WSDOT will be closing both directions of I-5 between Federal Way and Fife on Aug. 28 and 29 as part of its SR 167 Completion Project.

The work will involve moving 10 gigantic girders into place for the new 70th Avenue East Bridge.

Friday, Aug. 28 and Saturday, Aug. 29

  • I-5 lane closures begin at 8 p.m. on Friday
  • All lanes of I-5 will close at 11p.m. between 54th Avenue East in Fife and SR 18 in Federal Way
  • Lanes start to reopen by 8 a.m. Saturday
  • All lanes will reopen by noon Saturday

Saturday, Aug. 29 and Sunday, Aug. 30

  • I-5 lane closures begin at 8 p.m. Saturday
  • All lanes of I-5 will close at 11 p.m. between 54th Avenue East in Fife and SR 18 in Federal Way
  • Lanes start to reopen by 8 a.m. Sunday
  • All lanes will reopen by noon Sunday

Visit the WSDOT's website for more information.